To access the Contract Fund Package Summary, click the Funding tab on the Contract Administration Summary component. Locate the fund package, and select Open from the row Actions menu.
The Contract section holds information for each contract fund package, including a list of its associated funds. Click the Contract Fund Packages field, or use the arrow buttons on the subheader, to select the fund package you want to review.
You can view or change information in these fields:
Note: If you often use the same reference fund package as the default for contract adjustments, you can set the Default Contract Adjustment Indicator to the reference fund package so that it will always be marked as default when you add it to a cost estimate, project, or contract. You can set the Default Contract Adjustment Indicator for more than one fund package until you activate the contract.
Administration Overview - See Managing Contracts.
Contract Administration - See Maintaining a Contract.
Fund Package Assignment - See Assigning Funding to Contract Items.
Items - See Managing Contract Items.
Payment Estimate - See Maintaining Payment Estimate Information for a Contract.
Projects - See Managing Contract Projects.
Subcontracts - See Managing Subcontracts.
The component Actions menu has the following functions:
To add funds to this fund package, click the Select Funds button. See Adding Funds to a Fund Package.
The Funds in Package section displays a list of the funds in the fund package. You can view or change information in these fields:
The row Actions menu has the following functions:
By adding funds to a fund package, you are setting the funding sources and percent allocation for the fund package. Each funding source can be defined by percentage, limits, and priorities.
Click the Select Funds button.
The system displays a modal window for adding funding.
Type criteria in the Quick Find search box that matches the fund you want to add or click Show first 10.
The system lists all the funds that meet your search criteria.
Click the row for each fund you want to add to the package.
The system adds a check to the left of the row to indicate it is selected.
Click the Add to Fund Package button.
The system adds the selected funds to the fund package and closes the modal window.
Enter additional information about the fund as needed.
When you are finished, click the Save button.
Several conditions must be met in order to create a valid fund package when it contains more than one fund.
Because funds may have dollar limitations, you can select more than one fund for fund packages to provide adequate funding for the project. To create a valid fund package that contains more than one fund:
You must designate the order in which to use the funds. In the Priority field, type a 1 to indicate that the fund should be used first, type a 2 to indicate the fund that should be used second, and so on.
The priorities must be sequential, beginning with 1 and increased by an increment of 1. A fund may not have a priority of 0 or any negative number.
If you need more than one fund to pay for one priority, you can assign the same priority to more than one fund. In this case, you must also indicate the percentage of the work each fund will pay. The percentages for all the funds for one priority must total 100.
To ensure that the last priority fund pays for any excess not covered by limited funds from higher priorities, the fund for the last priority must be unlimited and at least one fund in each of the other priorities must have a limit.
Example:
A group of items in a project has federal, state, and municipal funding. The municipal funding is limited to $5000. After the $5000 is used, the federal and state funds will split the remaining
cost. The items would be assigned to fund package 1, which would have priority 1 funds for the federal, state, and municipal funds. The municipal fund would have the dollar limit set to $5000. There would also be priority 2 funds split between the
federal and state funds only, with no dollar limits set.