A contract change order must be approved by agency reviewers at several levels of authority before any changes can be made to the contract. Your agency determines a default structure for how many levels of approval are required for each change order type, at what stage each approval should take place, and which agency or non-agency user group has authority to approve each change order at each approval level.
A change order follows this typical workflow:
When a change order is ready for approval, the user with authority to approve is notified by email.
The approver reviews the change order and selects Approve, Reject, Deny, or Void from the Actions menu on the Contract Change Order Summary component header.
At each approval level, the approver must add a comment about his approval decision.
If the change order is rejected, the system records the decision, closes the approval round, and sets the change order's status to Rejected.
If the change order is denied, the system records the decision, closes the approval round, and sets the change order's status to Denied. Once denied, a change order cannot be changed or deleted, and will never be incorporated into the contract. (The only difference between the Denied and Voided status settings is that a change order that includes dollars or time cannot be voided.)
If the change order is voided, the system records the decision, closes the approval round, and sets the change order's status to Voided. Once voided, a change order cannot be changed or deleted, and will never be incorporated into the contract.
If approved as a member of a lower assigned approval group, the system records the decision and sends notification to members of the next higher approval group that it is ready for approval.
If approved as a member of the highest assigned approval group, the system changes its status to Approved and incorporates all the changes into the contract. Once the final approval is made, a change order cannot be changed or deleted.
To delete an approval tracking record from this change order, select Delete from the Actions menu on the approval group row. To reverse the deletion, click the Undo button.
Note: Approval tracking records cannot be deleted from a change order if a value has been entered in the Decision field.
When you are finished, click the Save button to apply your changes. The system displays a message to confirm that your changes were saved in the database.
You can assign default approval groups to the change order based on the definition of the change order, the contract type, and the reference change order approval rules defined in the system. Before the system allows you to submit a change order for approval, at least one approval group must be assigned to the change order, and any group marked as a “Minimum Approval Level” group that would be assigned as a default approval group is also required. If you submit the change order for approval before approval groups have been assigned to the change order, the system automatically adds the default approval groups before changing the change order's status to Pending Approval.
To add system default approval groups to the change order, go to the Contract Change Order Summary, click the Approval Tracking tab, and then select Assign Default Approval Groups from the list Actions menu. The system adds all the default approval groups according to your agency's change order approval rules. If a default approval group is already in the list, it is not duplicated.
Follow these steps to add one or more new approval groups for this change order:
On the Contract Change
Order Summary, click the Approval
Tracking tab, and then click the Add
Approval Group button.
The system displays a modal window
for adding approval groups.
Click in the Override Comments box and type information about why the approval groups are being added.
Locate the approval
group you want to add by typing criteria in the Quick Find search
box or by clicking Show first 10.
The system lists all the approval
groups that meet your search criteria.
Click the row for
each approval group you want to add.
The system adds a check mark beside
each approval group you select and shades the row. To cancel a selection,
click the selected row again.
Click the Save
button.
The system closes the modal window,
takes you to the Approval
Tracking tab with the new
approval groups added to the list, and saves each new approval group
with the Override
Action set to Added.
Follow these steps to remove an approval group that was added to the change order with the Assign Default Approval Groups action.
Note: The change order approval group Approval Group 1 is a required group. This group cannot be removed from the change order.
On the Contract Change
Order Summary, click the Approval
Tracking tab, and then select Remove
Approval Group from the Actions
menu on the approval group row.
The system displays a modal window
for removing approval groups.
Click in the Override Comments text box and type information about why the approval group is being removed.
Click the Save
button.
The system closes the modal window
and takes you to the Approval
Tracking tab. The removed
approval group is still displayed in the list, but saved with the
Override Action
set to Removed.
Maintaining a Contract Change Order