Projects have a validation process that generates a list of warnings about the state of the project. These warnings do not stop further processing.
The Validate Project command can be accessed by clicking the Actions menu on the Project Summary component header. The following information is validated when you select the Validate Project option:
The project contains at least one project item.
The project contains at least one county.
The sum of the project county percentages equals 100%.
The project contains at least one district.
The project contains at least one category.
If the Require Project Item Assigned to Category agency option is set to True, then all project items must be assigned to a category.
All project items must have a quantity.
blank, null are not valid
0 is a warning
All project items must have a price.
blank, null are not valid
0 is a warning
If the Bid Requirement Code field is set to Minimum for an item, the project item price must be greater than or equal to the value in the Unit Price Comparison field.
If the Bid Requirement Code field is set to Maximum for an item, the project item price must be less than or equal to the value in the Unit Price Comparison field.
The project contains a point location record with the word "midpoint" recorded in the Description field and recorded values for longitude and latitude.
All project items have been funded.
All fund packages associated with an item must pass funding validations.
All alternate sets attached to a project item must have an alternate member defined at the item level.
For each alternate set, there should be at least one item with an assigned set and member.
All alternate sets attached to a project category must have an alternate member defined at the category level.
For each category alternate set, there should be at least one category with an assigned set and member.