The calculations used by the system to determine the net amount of retainage for a progress or semi-final payment estimate depend on the retainage method and the settings for a number of other agency options. The following table provides detailed calculations for each potential configuration of these factors.
Row |
Retainage Method |
Agency Option Settings |
Calculations |
1 |
Work per period |
Retainage Calculation: Yes Retainage for Contract or Project: Contract Retainage Exempt for Subcontract Items: No Retainage Exempt for Stockpiles: No Contract Retainage Base: Current |
CURRENT_ITEM_PAID_GROSS_AMOUNT - [SUM for this payment estimate (CURRENT_PAID_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] + CURRENT_GROSS_CONTRACT_ADJUSTMENT_AMOUNT + CURRENT_GROSS_ITEM_ADJUSTMENT_AMOUNT = CURRENT_NET_AMOUNT_FOR_RETAINAGE |
2 |
Work in place |
Retainage Calculation: Yes Retainage for Contract or Project: Contract Retainage Exempt for Subcontract Items: No Retainage Exempt for Stockpiles: No Contract Retainage Base: Current |
TOTAL_ITEM_PAID_GROSS_AMOUNT - [SUM for all payment estimates (CURRENT_PAID_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] + TOTAL_GROSS_CONTRACT_ADJUSTMENT_AMOUNT + TOTAL_GROSS_ITEM_ADJUSTMENT_AMOUNT = TOTAL_NET_AMOUNT_FOR_RETAINAGE |
3 |
Work per period |
Retainage Calculation: Yes Retainage for Contract or Project: Contract Retainage Exempt for Subcontract Items: No Retainage Exempt for Stockpiles: Yes Contract Retainage Base: Current |
CURRENT_ITEM_PAID_GROSS_AMOUNT - [SUM (CURRENT_PAID_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] + CURRENT_GROSS_CONTRACT_ADJUSTMENT_AMOUNT + [CURRENT_GROSS_ITEM_ADJUSTMENT_AMOUNT - [SUM (ITEM_ADJUSTMENT_AMOUNT where ITEM_ADJUSTMENT_TYPE is "Construction Stockpile")] = CURRENT_NET_AMOUNT_FOR_RETAINAGE_CALCULATION |
4 |
Work in place |
Retainage Calculation: Yes Retainage for Contract or Project: Contract Retainage Exempt for Subcontract Items: No Retainage Exempt for Stockpiles: Yes Contract Retainage Base: Current |
[TOTAL_ITEM_PAID_GROSS_AMOUNT - SUM for all payment estimates (CURRENT_PAID_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] + [TOTAL_GROSS_CONTRACT_ADJUSTMENT_AMOUNT - SUM for all payment estimates (ITEM_ADJUSTMENT_AMOUNT where ITEM_ADJUSTMENT_TYPE is "Construction Stockpile")] = TOTAL _NET_AMOUNT_FOR_RETAINAGE |
5 |
Work per period |
Retainage Calculation: Yes Retainage for Contract or Project: Contract Payment Estimate's Contract has a Project Fund where FUNDTYPE is set to Federal Retainage Exempt for Subcontract Items: Yes Retainage Exempt for Stockpiles: No Contract Retainage Base: Current |
For each Payment Estimate Item where an associated DWR_POSTING_QTY (for current payment estimate) has CONTRACTOR not equal to PRIMEVENDOR_ID, calculate the percentage of work completed by the subcontractors for the Payment Estimate Item: Percentage of work by subcontractors for payment estimate item = Divide [SUM (DWR_POSTING_QTY associated to current PAYMENT ESTIMATE ITEM where CONTRACTOR does not equal PRIMEVENDOR_ID)] by CURRENT_INSTALLED_QUANTITY Next, calculate the installed amount for the subcontractors for the Payment Estimate Item: Installed Amount for Subcontractors for Payment Estimate Item = Multiply Percentage of work by Subcontractors for Payment Estimate Item" by CURRENT_INSTALLED_AMOUNT. Then, sum the "Installed Amount for Subcontractors for Payment Estimate Item" for all Payment Estimate Items: "Installed Amount for Subcontractors for All Payment Estimate Items" = SUM across all Payment Estimate Items ("Installed Amount for Subcontractors for Payment Estimate Item") CURRENT_ITEM_PAID_GROSS_AMOUNT minus [SUM (CURRENT_INSTALLED_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] plus CURRENT_GROSS_ITEM_ADJUSTMENT_AMOUNT minus "Installed Amount for Subcontractors for All Payment Estimate Items" (as calculated above) plus CURRENT_GROSS_CONTRACT_ADJUSTMENT_AMOUNT = CURRENT_NET_AMOUNT_FOR_RETAINAGE_CALCULATION. |
6 |
Work in place |
Retainage Calculation: Yes Retainage for Contract or Project: Contract Payment Estimate's Contract has a Project Fund where FUNDTYPE is set to Federal Retainage Exempt for Subcontract Items: Yes Retainage Exempt for Stockpiles: No Contract Retainage Base: Current |
For every Payment Estimate Item from every Payment Estimate where an associated DWR_POSTING_QTY has CONTRACTOR not equal to PRIMEVENDOR_ID, calculate the percentage of work completed by the subcontractors for the Payment Estimate Item: "Percentage of work by Subcontractors for Payment Estimate Item across all Payment Estimates" = Divide [SUM (DWR_POSTING_QTY associated to PAYMENT ESTIMATE ITEM where CONTRACTOR does not equal PRIMEVENDOR_ID)] by (PAYMENT ESTIMATE ITEM.CURRENT_INSTALLED_QUANTITY + PREVIOUS_TOTAL_INSTALLED_QUANTITY) Next, calculate the installed amount for the subcontractors for the Payment Estimate Item: "Installed Amount for Subcontractors for Payment Estimate Item across all Payment Estimates" = Multiply "Percentage of work by Subcontractors for Payment Estimate Item across all Payment Estimates" by [(CURRENT_INSTALLED_QUANTITY + PREVIOUS_TOTAL_INSTALLED_QUANTITY) multiplied by the unit price of the item. Then, sum the "Installed Amount for Subcontractors for Payment Estimate Item across all Payment Estimates" for all Payment Estimate Items: "Installed Amount for Subcontractors for All Payment Estimate Items for All Payment Estimates" = SUM across all Payment Estimate Items ("Installed Amount for Subcontractors for Payment Estimate Item across all Payment Estimates") TOTAL_ITEM_PAID_GROSS_AMOUNT minus [SUM (CURRENT_INSTALLED_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes") for all payment estimates] plus TOTAL_GROSS_ITEM_ADJUSTMENT_AMOUNT minus "Installed Amount for Subcontractors for All Payment Estimate Items for All Payment Estimates" (as calculated above) plus TOTAL_GROSS_CONTRACT_ADJUSTMENT_AMOUNT = TOTAL _NET_AMOUNT_FOR_RETAINAGE_CALCULATION. |
7 |
Work per period |
Retainage Calculation: Yes Retainage for Contract or Project: Contract Payment Estimate's Contract has a Project Fund where FUNDTYPE is set to Federal Retainage Exempt for Subcontract Items: Yes Retainage Exempt for Stockpiles: No Contract Retainage Base: Current |
For each Payment Estimate Item where an associated DWR_POSTING_QTY (for current payment estimate) has CONTRACTOR not equal to PRIMEVENDOR_ID, calculate the percentage of work completed by the subcontractors for the Payment Estimate Item: "Percentage of work by Subcontractors for Payment Estimate Item" = Divide [SUM (DWR_POSTING_QTY associated to current PAYMENT ESTIMATE ITEM where CONTRACTOR does not equal PRIMEVENDOR_ID)] by CURRENT_INSTALLED_QUANTITY Next, calculate the installed amount for the subcontractors for the Payment Estimate Item: "Installed Amount for Subcontractors for Payment Estimate Item" = Multiply "Percentage of work by Subcontractors for Payment Estimate Item" by CURRENT_INSTALLED_AMOUNT Then, sum the "Installed Amount for Subcontractors for Payment Estimate Item" for all Payment Estimate Items: "Installed Amount for Subcontractors for All Payment Estimate Items" = SUM across all Payment Estimate Items ("Installed Amount for Subcontractors for Payment Estimate Item") CURRENT_ITEM_PAID_GROSS_AMOUNT minus [SUM (CURRENT_INSTALLED_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] plus [CURRENT_GROSS_ITEM_ADJUSTMENT_AMOUNT - SUM (ITEM_ADJUSTMENT_AMOUNT where ITEM_ADJUSTMENT_TYPE is "Construction Stockpile")] minus "Installed Amount for Subcontractors for All Payment Estimate Items" (as calculated above) plus CURRENT_GROSS_CONTRACT_ADJUSTMENT_AMOUNT = CURRENT_NET_AMOUNT_FOR_RETAINAGE_CALCULATION. |
8 |
Work in place |
Retainage Calculation: Yes Retainage for Contract or Project: Contract Payment Estimate's Contract has a Project Fund where FUNDTYPE is set to Federal Retainage Exempt for Subcontract Items: Yes Retainage Exempt for Stockpiles: No Contract Retainage Base: Current |
For every Payment Estimate Item from every Payment Estimate where an associated DWR_POSTING_QTY has CONTRACTOR not equal to PRIMEVENDOR_ID, calculate the percentage of work completed by the subcontractors for the Payment Estimate Item: "Percentage of work by Subcontractors for Payment Estimate Item across all Payment Estimates" = Divide [SUM (DWR_POSTING_QTY associated to PAYMENT ESTIMATE ITEM where CONTRACTOR does not equal PRIMEVENDOR_ID)] by (CURRENT_INSTALLED_QUANTITY + PREVIOUS_TOTAL_INSTALLED_QUANTITY) Next, calculate the installed amount for the subcontractors for the Payment Estimate Item: "Installed Amount for Subcontractors for Payment Estimate Item across all Payment Estimates" = Multiply "Percentage of work by Subcontractors for Payment Estimate Item across all Payment Estimates" by [(CURRENT_INSTALLED_QUANTITY + PREVIOUS_TOTAL_INSTALLED_QUANTITY) multiplied by the unit price of the item]. Then, sum the "Installed Amount for Subcontractors for Payment Estimate Item across all Payment Estimates" for all Payment Estimate Items: "Installed Amount for Subcontractors for All Payment Estimate Items for All Payment Estimates" = SUM across all Payment Estimate Items ("Installed Amount for Subcontractors for Payment Estimate Item across all Payment Estimates") TOTAL_ITEM_PAID_GROSS_AMOUNT minus [SUM (CURRENT_INSTALLED_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes") for all payment estimates] plus [TOTAL_GROSS_ITEM_ADJUSTMENT_AMOUNT - SUM for all payment estimates (ITEM_ADJUSTMENT_AMOUNT where ITEM_ADJUSTMENT_TYPE is "Construction Stockpile")] minus "Installed Amount for Subcontractors for All Payment Estimate Items for All Payment Estimates" (as calculated above) plus TOTAL_GROSS_CONTRACT_ADJUSTMENT_AMOUNT = TOTAL _NET_AMOUNT_FOR_RETAINAGE_CALCULATION. |
9 |
Work per period |
Retainage Calculation: Yes Retainage for Contract or Project: Contract Retainage Exempt for Subcontract Items: No Retainage Exempt for Stockpiles: No Contract Retainage Base: Award |
CURRENT_ITEM_PAID_GROSS_AMOUNT - [SUM for current payment estimate (CURRENT_PAID_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] - [SUM for current payment estimate (CURRENT_PAID_AMOUNT where associated ITEMSOURCE is "Change Order" or "Modified Change Order")] + CURRENT_GROSS_CONTRACT_ADJUSTMENT_AMOUNT + CURRENT_GROSS_ITEM_ADJUSTMENT_AMOUNT = CURRENT_NET_AMOUNT_FOR_RETAINAGE_CALCULATION. |
10 |
Work in place |
Retainage Calculation: Yes Retainage for Contract or Project: Contract Retainage Exempt for Subcontract Items: No Retainage Exempt for Stockpiles: No Contract Retainage Base: Award |
TOTAL_ITEM_PAID_GROSS_AMOUNT - [SUM for all payment estimates (CURRENT_PAID_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] - [SUM for all payment estimates (CURRENT_PAID_AMOUNT where associated ITEMSOURCE is "Change Order" or "Modified Change Order")] + TOTAL_GROSS_CONTRACT_ADJUSTMENT_AMOUNT + TOTAL_GROSS_ITEM_ADJUSTMENT_AMOUNT = TOTAL _NET_AMOUNT_FOR_RETAINAGE_CALCULATION |
11 |
Work per period |
Retainage Calculation: Yes Retainage for Contract or Project: Contract Retainage Exempt for Subcontract Items: No Retainage Exempt for Stockpiles: Yes Contract Retainage Base: Award |
CURRENT_ITEM_PAID_GROSS_AMOUNT - [SUM for current payment estimate (CURRENT_PAID_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] - [SUM for current payment estimate CURRENT_PAID_AMOUNT where associated ITEMSOURCE is "Change Order" or "Modified Change Order")] + CURRENT_GROSS_CONTRACT_ADJUSTMENT_AMOUNT + [CURRENT_GROSS_ITEM_ADJUSTMENT_AMOUNT - SUM for current payment estimate (ITEM_ADJUSTMENT_AMOUNT where ITEM_ADJUSTMENT_TYPE is "Construction Stockpile")] = CURRENT_NET_AMOUNT_FOR_RETAINAGE_CALCULATION |
12 |
Work in place |
Retainage Calculation: Yes Retainage for Contract or Project: Contract Retainage Exempt for Subcontract Items: No Retainage Exempt for Stockpiles: Yes Contract Retainage Base: Award |
[TOTAL_ITEM_PAID_GROSS_AMOUNT - [SUM for all payment estimates (CURRENT_PAID_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] - [SUM for all payment estimates (CURRENT_PAID_AMOUNT where associated ITEMSOURCE is "Change Order" or "Modified Change Order")] + [TOTAL_GROSS_CONTRACT_ADJUSTMENT_AMOUNT - SUM for all payment estimates (ITEM_ADJUSTMENT_AMOUNT where ITEM_ADJUSTMENT_TYPE is "Construction Stockpile")] = TOTAL_NET_AMOUNT_FOR_RETAINAGE_CALCULATION |
13 |
Work per period |
Retainage Calculation: Yes Retainage for Contract or Project: Contract Payment Estimate's Contract has a Project Fund where FUNDTYPE is set to Federal Retainage Exempt for Subcontract Items: Yes Retainage Exempt for Stockpiles: No Contract Retainage Base: Award |
Note: If no Federal Project Fund exists for the Contract, the system uses the calculations in Row 9. For each Payment Estimate Item where associated ITEMSOURCE is equal to "Original" or "Modified Original" AND where an associated DWR_POSTING_QTY (for current payment estimate) has CONTRACTOR not equal to PRIMEVENDOR_ID, calculate the percentage of work completed by the subcontractors for the Payment Estimate Item: "Percentage of work by Subcontractors for Payment Estimate Item" = Divide [SUM (DWR_POSTING_QTY associated to current PAYMENT ESTIMATE ITEM where CONTRACTOR does not equal PRIMEVENDOR_ID)] by CURRENT_INSTALLED_QUANTITY Next, calculate the installed amount for the subcontractors for the Payment Estimate Item: "Installed Amount for Subcontractors for Payment Estimate Item" = Multiply "Percentage of work by Subcontractors for Payment Estimate Item" by CURRENT_INSTALLED_AMOUNT Then, sum the "Installed Amount for Subcontractors for Payment Estimate Item" for all Payment Estimate Items: "Installed Amount for Subcontractors for All Payment Estimate Items" = SUM across all Payment Estimate Items ("Installed Amount for Subcontractors for Payment Estimate Item") CURRENT_ITEM_PAID_GROSS_AMOUNT minus [SUM for current payment estimate (CURRENT_INSTALLED_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] minus [SUM for current payment estimate (CURRENT_INSTALLED_AMOUNT where associated ITEMSOURCE is "Change Order" or "Modified Change Order")] plus CURRENT_GROSS_ITEM_ADJUSTMENT_AMOUNT minus "Installed Amount for Subcontractors for All Payment Estimate Items" (as calculated above) plus CURRENT_GROSS_CONTRACT_ADJUSTMENT_AMOUNT = CURRENT_NET_AMOUNT_FOR_RETAINAGE_CALCULATION |
14 |
Work in place |
Retainage Calculation: Yes Retainage for Contract or Project: Contract Payment Estimate's Contract has a Project Fund where FUNDTYPE is set to Federal Retainage Exempt for Subcontract Items: Yes Retainage Exempt for Stockpiles: No Contract Retainage Base: Award |
Note: If no Federal Project Fund exists for the Contract, the system uses the calculations in Row 10. For each Payment Estimate Item where associated ITEMSOURCE is equal to "Original" or "Modified Original" AND where an associated DWR_POSTING_QTY has CONTRACTOR not equal to PRIMEVENDOR_ID, calculate the percentage of work completed by the subcontractors for the Payment Estimate Item: "Percentage of work by Subcontractors for Payment Estimate Item across all Payment Estimates" = Divide [SUM (DWR_POSTING_QTY associated to PAYMENT ESTIMATE ITEM where CONTRACTOR does not equal PRIMEVENDOR_ID)] by (CURRENT_INSTALLED_QUANTITY + PREVIOUS_TOTAL_INSTALLED_QUANTITY) Next, calculate the installed amount for the subcontractors for the Payment Estimate Item: "Installed Amount for Subcontractors for Payment Estimate Item across all Payment Estimates" = Multiply "Percentage of work by Subcontractors for Payment Estimate Item across all Payment Estimates" by [(CURRENT_INSTALLED_QUANTITY + PREVIOUS_TOTAL_INSTALLED_QUANTITY) multiplied by the unit price of the item]. Then, sum the "Installed Amount for Subcontractors for Payment Estimate Item across all Payment Estimates" for all Payment Estimate Items: "Installed Amount for Subcontractors for All Payment Estimate Items for All Payment Estimates" = SUM across all Payment Estimate Items ("Installed Amount for Subcontractors for Payment Estimate Item across all Payment Estimates") TOTAL_ITEM_PAID_GROSS_AMOUNT minus [SUM for all payment estimates (CURRENT_INSTALLED_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] minus [SUM for all payment estimates (CURRENT_INSTALLED_AMOUNT where associated ITEMSOURCE is "Change Order" or "Modified Change Order")] plus TOTAL_GROSS_ITEM_ADJUSTMENT_AMOUNT minus "Installed Amount for Subcontractors for All Payment Estimate Items for All Payment Estimates" plus TOTAL_GROSS_CONTRACT_ADJUSTMENT_AMOUNT = TOTAL_NET_AMOUNT_FOR_RETAINAGE_CALCULATION |
15 |
Work per period |
Retainage Calculation: Yes Retainage for Contract or Project: Contract Payment Estimate's Contract has a Project Fund where FUNDTYPE is set to Federal Retainage Exempt for Subcontract Items: Yes Retainage Exempt for Stockpiles: Yes Contract Retainage Base: Award |
Note: If no Federal Project Fund exists for the Contract, the system uses the calculations in Row 11. For each Payment Estimate Item where associated ITEMSOURCE is equal to "Original" or "Modified Original" AND where an associated DWR_POSTING_QTY (for current payment estimate) has CONTRACTOR not equal to PRIMEVENDOR_ID, calculate the percentage of work completed by the subcontractors for the Payment Estimate Item: "Percentage of work by Subcontractors for Payment Estimate Item" = Divide [SUM (DWR_POSTING_QTY associated to current PAYMENT ESTIMATE ITEM where CONTRACTOR does not equal PRIMEVENDOR_ID)] by CURRENT_INSTALLED_QUANTITY Next, calculate the installed amount for the subcontractors for the Payment Estimate Item: "Installed Amount for Subcontractors for Payment Estimate Item" = Multiply "Percentage of work by Subcontractors for Payment Estimate Item" by CURRENT_INSTALLED_AMOUNT Then, sum the "Installed Amount for Subcontractors for Payment Estimate Item" for all Payment Estimate Items: "Installed Amount for Subcontractors for All Payment Estimate Items" = SUM across all Payment Estimate Items ("Installed Amount for Subcontractors for Payment Estimate Item") CURRENT_ITEM_PAID_GROSS_AMOUNT minus [SUM for current payment estimate (CURRENT_INSTALLED_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] minus [SUM for current payment estimate (CURRENT_INSTALLED_AMOUNT where associated ITEMSOURCE is "Change Order" or "Modified Change Order")] plus [CURRENT_GROSS_ITEM_ADJUSTMENT_AMOUNT - SUM (ITEM_ADJUSTMENT_AMOUNT where ITEM_ADJUSTMENT_TYPE is "Construction Stockpile")] minus "Installed Amount for Subcontractors for All Payment Estimate Items" (as calculated above) plus CURRENT_GROSS_CONTRACT_ADJUSTMENT_AMOUNT = CURRENT_NET_AMOUNT_FOR_RETAINAGE_CALCULATION. |
16 |
Work in place |
Retainage Calculation: Yes Retainage for Contract or Project: Contract Payment Estimate's Contract has a Project Fund where FUNDTYPE is set to Federal Retainage Exempt for Subcontract Items: Yes Retainage Exempt for Stockpiles: Yes Contract Retainage Base: Award |
Note: If no Federal Project Fund exists for the Contract, the system uses the calculations in Row 12. For each Payment Estimate Item where associated ITEMSOURCE is equal to "Original" or "Modified Original" AND where an associated DWR_POSTING_QTY has CONTRACTOR not equal to PRIMEVENDOR_ID, calculate the percentage of work completed by the subcontractors for the Payment Estimate Item: "Percentage of work by Subcontractors for Payment Estimate Item across all Payment Estimates" = Divide [SUM (DWR_POSTING_QTY associated to PAYMENT ESTIMATE ITEM where CONTRACTOR does not equal PRIMEVENDOR_ID)] by (CURRENT_INSTALLED_QUANTITY + PREVIOUS_TOTAL_INSTALLED_QUANTITY) Next, calculate the installed amount for the subcontractors for the Payment Estimate Item: "Installed Amount for Subcontractors for Payment Estimate Item across all Payment Estimates" = Multiply "Percentage of work by Subcontractors for Payment Estimate Item across all Payment Estimates" by [(CURRENT_INSTALLED_QUANTITY + PREVIOUS_TOTAL_INSTALLED_QUANTITY) multiplied by the unit price of the item]. Then, sum the "Installed Amount for Subcontractors for Payment Estimate Item across all Payment Estimates" for all Payment Estimate Items: "Installed Amount for Subcontractors for All Payment Estimate Items for All Payment Estimates" = SUM across all Payment Estimate Items ("Installed Amount for Subcontractors for Payment Estimate Item across all Payment Estimates") TOTAL_ITEM_PAID_GROSS_AMOUNT minus [SUM for all payment estimates (CURRENT_INSTALLED_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] minus [SUM for all payment estimates (CURRENT_INSTALLED_AMOUNT where associated ITEMSOURCE is "Change Order" or "Modified Change Order")] plus [TOTAL_GROSS_ITEM_ADJUSTMENT_AMOUNT - SUM for all payment estimates (ITEM_ADJUSTMENT_AMOUNT where ITEM_ADJUSTMENT_TYPE is "Construction Stockpile")] minus "Installed Amount for Subcontractors for All Payment Estimate Items for All Payment Estimates" plus TOTAL_GROSS_CONTRACT_ADJUSTMENT_AMOUNT = TOTAL _NET_AMOUNT_FOR_RETAINAGE_CALCULATION |
17 |
Work per period |
Retainage Calculation: Yes Retainage for Contract or Project: Project Retainage Exempt for Subcontract Items: No Retainage Exempt for Stockpiles: No Contract Retainage Base: Current |
CURRENT_ITEM_PAID_GROSS_AMOUNT - [SUM for current payment estimate project (CURRENT_PAID_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] + CURRENT_GROSS_ESTIMATE_CONTRACT_ ADJUSTMENT_PROJECT_DISTRIBUTION_AMOUNT + CURRENT_GROSS_ITEM_ADJUSTMENT_AMOUNT = CURRENT_NET_AMOUNT_FOR_RETAINAGE_CALCULATION |
18 |
Work in place |
Retainage Calculation: Yes Retainage for Contract or Project: Project Retainage Exempt for Subcontract Items: No Retainage Exempt for Stockpiles: No Contract Retainage Base: Current |
TOTAL_ITEM_PAID_GROSS_AMOUNT - [SUM for all payment estimate projects (CURRENT_PAID_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] + TOTAL_GROSS_ESTIMATE_CONTRACT_ ADJUSTMENT_PROJECT_DISTRIBUTION_AMOUNT + TOTAL_GROSS_ITEM_ADJUSTMENT_AMOUNT = TOTAL_NET_AMOUNT_FOR_RETAINAGE_CALCULATION |
19 |
Work per period |
Retainage Calculation: Yes Retainage for Contract or Project: Project Retainage Exempt for Subcontract Items: No Retainage Exempt for Stockpiles: Yes Contract Retainage Base: Current |
CURRENT_ITEM_PAID_GROSS_AMOUNT - [SUM for current payment estimate project (CURRENT_PAID_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] + CURRENT_GROSS_ESTIMATE_CONTRACT_ ADJUSTMENT_PROJECT_DISTRIBUTION_AMOUNT + [CURRENT_GROSS_ITEM_ADJUSTMENT_AMOUNT - [SUM for current payment estimate project (ITEM_ADJUSTMENT_AMOUNT where ITEM_ADJUSTMENT_TYPE is "Construction Stockpile")] = CURRENT_NET_AMOUNT_FOR_RETAINAGE_CALCULATION |
20 |
Work in place |
Retainage Calculation: Yes Retainage for Contract or Project: Project Retainage Exempt for Subcontract Items: No Retainage Exempt for Stockpiles: Yes Contract Retainage Base: Current |
TOTAL_ITEM_PAID_GROSS_AMOUNT - [SUM for all payment estimate projects (CURRENT_PAID_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] + TOTAL_GROSS_ESTIMATE_CONTRACT_ ADJUSTMENT_PROJECT_DISTRIBUTION_AMOUNT + [TOTAL_GROSS_ITEM_ADJUSTMENT_AMOUNT - SUM for all payment estimate projects (ITEM_ADJUSTMENT_AMOUNT where ITEM_ADJUSTMENT_TYPE is "Construction Stockpile")] = TOTAL_NET_AMOUNT_FOR_RETAINAGE_CALCULATION |
21 |
Work per period |
Retainage Calculation: Yes Retainage for Contract or Project: Project Payment Estimate's Contract has a Project Fund where FUNDTYPE is set to Federal Retainage Exempt for Subcontract Items: Yes Retainage Exempt for Stockpiles: No Contract Retainage Base: Current |
Note: If no Federal Project Fund exists for the Contract, the system uses the calculations in Row 17. For each Payment Estimate Item for Payment Estimate Project where an associated DWR_POSTING_QTY (for current payment estimate project) has CONTRACTOR not equal to PRIMEVENDOR_ID, calculate the percentage of work completed by the subcontractors for the Payment Estimate Item: "Percentage of work by Subcontractors for Payment Estimate Item" = Divide [SUM (DWR_POSTING_QTY associated to current PAYMENT ESTIMATE ITEM where CONTRACTOR does not equal PRIMEVENDOR_ID)] by CURRENT_INSTALLED_QUANTITY Next, calculate the installed amount for the subcontractors for the Payment Estimate Item: "Installed Amount for Subcontractors for Payment Estimate Item" = Multiply "Percentage of work by Subcontractors for Payment Estimate Item" by CURRENT_INSTALLED_AMOUNT Then, sum the "Installed Amount for Subcontractors for Payment Estimate Item" for all Payment Estimate Items: "Installed Amount for Subcontractors for All Payment Estimate Items" = SUM across all Payment Estimate Items ("Installed Amount for Subcontractors for Payment Estimate Item") CURRENT_ITEM_PAID_GROSS_AMOUNT minus [SUM for current payment estimate project (CURRENT_INSTALLED_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] plus CURRENT_GROSS_ESTIMATE_CONTRACT_ ADJUSTMENT_PROJECT_DISTRIBUTION_AMOUNT minus "Installed Amount for Subcontractors for All Payment Estimate Items" (as calculated above) plus CURRENT_GROSS_CONTRACT_ADJUSTMENT_AMOUNT = CURRENT_NET_AMOUNT_FOR_RETAINAGE_CALCULATION. |
22 |
Work in place |
Retainage Calculation: Yes Retainage for Contract or Project: Project Payment Estimate's Contract has a Project Fund where FUNDTYPE is set to Federal Retainage Exempt for Subcontract Items: Yes Retainage Exempt for Stockpiles: No Contract Retainage Base: Current |
Note: If no Federal Project Fund exists for the Contract, the system uses the calculations in Row 18. For every Payment Estimate Item that has been included on a Payment Estimate Project for the current Payment Estimate Project's Contract Project where an associated DWR_POSTING_QTY has CONTRACTOR not equal to PRIMEVENDOR_ID, calculate the percentage of work completed by the subcontractors for the Payment Estimate Item: "Percentage of work by Subcontractors for Payment Estimate Item across all Payment Estimate Projects" = Divide [SUM (DWR_POSTING_QTY associated to PAYMENT ESTIMATE ITEM where CONTRACTOR does not equal PRIMEVENDOR_ID)] by (CURRENT_INSTALLED_QUANTITY + PREVIOUS_TOTAL_INSTALLED_QUANTITY) Next, calculate the installed amount for the subcontractors for the Payment Estimate Item: "Installed Amount for Subcontractors for Payment Estimate Item across all Payment Estimate Projects" = Multiply "Percentage of work by Subcontractors for Payment Estimate Item across all Payment Estimate Projects" by [(CURRENT_INSTALLED_QUANTITY + PREVIOUS_TOTAL_INSTALLED_QUANTITY) multiplied by the unit price of the item. Then, sum the "Installed Amount for Subcontractors for Payment Estimate Item across all Payment Estimate Projects" for all Payment Estimate Items: "Installed Amount for Subcontractors for All Payment Estimate Items for All Payment Estimate Projects" = SUM across all Payment Estimate Items ("Installed Amount for Subcontractors for Payment Estimate Item across all Payment Estimate Projects") TOTAL_ITEM_PAID_GROSS_AMOUNT minus [SUM for all payment estimate projects (CURRENT_INSTALLED_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] plus TOTAL_GROSS_ITEM_ADJUSTMENT_AMOUNT minus "Installed Amount for Subcontractors for All Payment Estimate Items for All Payment Estimate Projects" (as calculated above) plus TOTAL_GROSS_ESTIMATE_ CONTRACT_ADJUSTMENT_PROJECT_DISTRIBUTION_AMOUNT = TOTAL_NET_AMOUNT_FOR_RETAINAGE_CALCULATION |
23 |
Work per period |
Retainage Calculation: Yes Retainage for Contract or Project: Project Payment Estimate's Contract has a Project Fund where FUNDTYPE is set to Federal Retainage Exempt for Subcontract Items: Yes Retainage Exempt for Stockpiles: Yes Contract Retainage Base: Current |
Note: If no Federal Project Fund exists for the Contract, the system uses the calculations in Row 19. For each Payment Estimate Item for Payment Estimate Project where an associated DWR_POSTING_QTY (for current payment estimate project) has CONTRACTOR not equal to PRIMEVENDOR_ID, calculate the percentage of work completed by the subcontractors for the Payment Estimate Item: "Percentage of work by Subcontractors for Payment Estimate Item" = Divide [SUM (DWR_POSTING_QTY associated to current PAYMENT ESTIMATE ITEM where CONTRACTOR does not equal PRIMEVENDOR_ID)] by CURRENT_INSTALLED_QUANTITY Next, calculate the installed amount for the subcontractors for the Payment Estimate Item: "Installed Amount for Subcontractors for Payment Estimate Item" = Multiply "Percentage of work by Subcontractors for Payment Estimate Item" by CURRENT_INSTALLED_AMOUNT Then, sum the "Installed Amount for Subcontractors for Payment Estimate Item" for all Payment Estimate Items: "Installed Amount for Subcontractors for All Payment Estimate Items" = SUM across all Payment Estimate Items ("Installed Amount for Subcontractors for Payment Estimate Item") CURRENT_ITEM_PAID_GROSS_AMOUNT minus [SUM for current payment estimate project (CURRENT_INSTALLED_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] plus [CURRENT_GROSS_ITEM_ADJUSTMENT_AMOUNT minus SUM for current payment estimate project (ITEM_ADJUSTMENT_AMOUNT where ITEM_ADJUSTMENT_TYPE is "Construction Stockpile")] minus "Installed Amount for Subcontractors for All Payment Estimate Items" (as calculated above) plus CURRENT_GROSS_ESTIMATE_CONTRACT_ ADJUSTMENT_PROJECT_DISTRIBUTION_AMOUNT = CURRENT_NET_AMOUNT_FOR_RETAINAGE_CALCULATION |
24 |
Work in place |
Retainage Calculation: Yes Retainage for Contract or Project: Project Payment Estimate's Contract has a Project Fund where FUNDTYPE is set to Federal Retainage Exempt for Subcontract Items: Yes Retainage Exempt for Stockpiles: Yes Contract Retainage Base: Current |
Note: If no Federal Project Fund exists for the Contract, the system uses the calculations in Row 20. For every Payment Estimate Item that has been included on a Payment Estimate Project for the current Payment Estimate Project's Contract Project where an associated DWR_POSTING_QTY has CONTRACTOR not equal to PRIMEVENDOR_ID, calculate the percentage of work completed by the subcontractors for the Payment Estimate Item: "Percentage of work by Subcontractors for Payment Estimate Item across all Payment Estimate Projects" = Divide [SUM (DWR_POSTING_QTY associated to PAYMENT ESTIMATE ITEM where CONTRACTOR does not equal PRIMEVENDOR_ID)] by (CURRENT_INSTALLED_QUANTITY + PREVIOUS_TOTAL_INSTALLED_QUANTITY) Next, calculate the installed amount for the subcontractors for the Payment Estimate Item: "Installed Amount for Subcontractors for Payment Estimate Item across all Payment Estimate Projects" = Multiply "Percentage of work by Subcontractors for Payment Estimate Item across all Payment Estimate Projects" by [(CURRENT_INSTALLED_QUANTITY + REVIOUS_TOTAL_INSTALLED_QUANTITY) multiplied by the unit price of the item. Then, sum the "Installed Amount for Subcontractors for Payment Estimate Item across all Payment Estimate Projects" for all Payment Estimate Items: "Installed Amount for Subcontractors for All Payment Estimate Items for All Payment Estimate Projects" = SUM across all Payment Estimate Items ("Installed Amount for Subcontractors for Payment Estimate Item across all Payment Estimate Projects") TOTAL_ITEM_PAID_GROSS_AMOUNT minus [SUM for all payment estimate projects (CURRENT_INSTALLED_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] plus [TOTAL_GROSS_ITEM_ADJUSTMENT_AMOUNT minus SUM for all payment estimate projects (ITEM_ADJUSTMENT_AMOUNT where ITEM_ADJUSTMENT_TYPE is "Construction Stockpile")] minus "Installed Amount for Subcontractors for All Payment Estimate Items for All Payment Estimate Projects" (as calculated above) plus TOTAL_GROSS_ESTIMATE_CONTRACT_ ADJUSTMENT_PROJECT_DISTRIBUTION_AMOUNT = TOTAL_NET_AMOUNT_FOR_RETAINAGE_CALCULATION |
25 |
Work per period |
Retainage Calculation: Yes Retainage for Contract or Project: Project Retainage Exempt for Subcontract Items: No Retainage Exempt for Stockpiles: No Contract Retainage Base: Award |
CURRENT_ITEM_PAID_GROSS_AMOUNT - [SUM for current payment estimate project (CURRENT_PAID_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] - [SUM for current payment estimate project (CURRENT_PAID_AMOUNT where associated ITEMSOURCE is "Change Order" or "Modified Change Order")] + CURRENT_GROSS_ESTIMATE_CONTRACT_ ADJUSTMENT_PROJECT_DISTRIBUTION_AMOUNT + CURRENT_GROSS_ITEM_ADJUSTMENT_AMOUNT = CURRENT_NET_AMOUNT_FOR_RETAINAGE_CALCULATION |
26 |
Work in place |
Retainage Calculation: Yes Retainage for Contract or Project: Project Retainage Exempt for Subcontract Items: No Retainage Exempt for Stockpiles: No Contract Retainage Base: Award |
TOTAL_ITEM_PAID_GROSS_AMOUNT - [SUM for all payment estimate projects (CURRENT_PAID_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] - [SUM for all payment estimate projects (CURRENT_PAID_AMOUNT where associated ITEMSOURCE is "Change Order" or "Modified Change Order")] + TOTAL_GROSS_ESTIMATE_CONTRACT_ ADJUSTMENT_PROJECT_DISTRIBUTION_AMOUNT + TOTAL_GROSS_ITEM_ADJUSTMENT_AMOUNT = TOTAL _NET_AMOUNT_FOR_RETAINAGE_CALCULATION |
27 |
Work per period |
Retainage Calculation: Yes Retainage for Contract or Project: Project Retainage Exempt for Subcontract Items: No Retainage Exempt for Stockpiles: Yes Contract Retainage Base: Award |
CURRENT_ITEM_PAID_GROSS_AMOUNT - [SUM for current payment estimate project (CURRENT_PAID_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] - [SUM for current payment estimate project (CURRENT_PAID_AMOUNT where associated ITEMSOURCE is "Change Order" or "Modified Change Order")] + CURRENT_GROSS_ESTIMATE_CONTRACT_ ADJUSTMENT_PROJECT_DISTRIBUTION_AMOUNT + [CURRENT_GROSS_ITEM_ADJUSTMENT_AMOUNT - [SUM for current payment estimate project (ITEM_ADJUSTMENT_AMOUNT where ITEM_ADJUSTMENT_TYPE is "Construction Stockpile")] = CURRENT_NET_AMOUNT_FOR_RETAINAGE_CALCULATION |
28 |
Work in place |
Retainage Calculation: Yes Retainage for Contract or Project: Project Retainage Exempt for Subcontract Items: No Retainage Exempt for Stockpiles: Yes Contract Retainage Base: Award |
TOTAL_ITEM_PAID_GROSS_AMOUNT - [SUM for all payment estimate projects (CURRENT_PAID_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] - [SUM for all payment estimate projects (CURRENT_PAID_AMOUNT where associated ITEMSOURCE is "Change Order" or "Modified Change Order")] + TOTAL_GROSS_ESTIMATE_CONTRACT_ ADJUSTMENT_PROJECT_DISTRIBUTION_AMOUNT + [TOTAL_GROSS_ITEM_ADJUSTMENT_AMOUNT - [SUM (ITEM_ADJUSTMENT_AMOUNT where ITEM_ADJUSTMENT_TYPE is "Construction Stockpile") for all payment estimates]] = TOTAL_NET_AMOUNT_FOR_RETAINAGE_CALCULATION |
29 |
Work per period |
Retainage Calculation: Yes Retainage for Contract or Project: Project Payment Estimate's Contract has a Project Fund where FUNDTYPE is set to Federal Retainage Exempt for Subcontract Items: Yes Retainage Exempt for Stockpiles: No Contract Retainage Base: Award |
Note: If no Federal Project Fund exists for the Contract, the system uses the calculations in Row 25. For each Payment Estimate Item for Payment Estimate Project where associated ITEMSOURCE is equal to "Original" or "Modified Original" AND where an associated DWR_POSTING_QTY (for current payment estimate project) has CONTRACTOR not equal to PRIMEVENDOR_ID, calculate the percentage of work completed by the subcontractors for the Payment Estimate Item: "Percentage of work by Subcontractors for Payment Estimate Item" = Divide [SUM (DWR_POSTING_QTY associated to current PAYMENT ESTIMATE ITEM where CONTRACTOR does not equal PRIMEVENDOR_ID)] by CURRENT_INSTALLED_QUANTITY Next, calculate the installed amount for the subcontractors for the Payment Estimate Item: "Installed Amount for Subcontractors for Payment Estimate Item" = Multiply "Percentage of work by Subcontractors for Payment Estimate Item" by CURRENT_INSTALLED_AMOUNT Then, sum the "Installed Amount for Subcontractors for Payment Estimate Item" for all Payment Estimate Items: "Installed Amount for Subcontractors for All Payment Estimate Items" = SUM across all Payment Estimate Items ("Installed Amount for Subcontractors for Payment Estimate Item") CURRENT_ITEM_PAID_GROSS_AMOUNT minus [SUM for current payment estimate project (CURRENT_INSTALLED_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] minus [SUM for current payment estimate project (CURRENT_INSTALLED_AMOUNT where associated ITEMSOURCE is "Change Order" or "Modified Change Order")] plus CURRENT_GROSS_ITEM_ADJUSTMENT_AMOUNT minus "Installed Amount for Subcontractors for All Payment Estimate Items" (as calculated above) plus CURRENT_GROSS_ESTIMATE_CONTRACT_ ADJUSTMENT_PROJECT_DISTRIBUTION_AMOUNT = CURRENT_NET_AMOUNT_FOR_RETAINAGE_CALCULATION. |
30 |
Work in place |
Retainage Calculation: Yes Retainage for Contract or Project: Project Payment Estimate's Contract has a Project Fund where FUNDTYPE is set to Federal Retainage Exempt for Subcontract Items: Yes Retainage Exempt for Stockpiles: No Contract Retainage Base: Award |
Note: If no Federal Project Fund exists for the Contract, the system uses the calculations in Row 26. For every Payment Estimate Item that has been included on a Payment Estimate Project for the current Payment Estimate Project's Contract Project where associated ITEMSOURCE is equal to "Original" or "Modified Original" AND where an associated DWR_POSTING_QTY has CONTRACTOR not equal to PRIMEVENDOR_ID, calculate the percentage of work completed by the subcontractors for the Payment Estimate Item: "Percentage of work by Subcontractors for Payment Estimate Item across all Payment Estimate Projects" = Divide [SUM (DWR_POSTING_QTY associated to PAYMENT ESTIMATE ITEM where CONTRACTOR does not equal PRIMEVENDOR_ID)] by (CURRENT_INSTALLED_QUANTITY + REVIOUS_TOTAL_INSTALLED_QUANTITY) Next, calculate the installed amount for the subcontractors for the Payment Estimate Item: "Installed Amount for Subcontractors for Payment Estimate Item across all Payment Estimate Projects" = Multiply "Percentage of work by Subcontractors for Payment Estimate Item across all Payment Estimate Projects" by [(CURRENT_INSTALLED_QUANTITY + REVIOUS_TOTAL_INSTALLED_QUANTITY) multiplied by the unit price of the item]. Then, sum the "Installed Amount for Subcontractors for Payment Estimate Item across all Payment Estimate Projects" for all Payment Estimate Items: "Installed Amount for Subcontractors for All Payment Estimate Items for All Payment Estimate Projects" = SUM across all Payment Estimate Items ("Installed Amount for Subcontractors for Payment Estimate Item across all Payment Estimate Projects") TOTAL_ITEM_PAID_GROSS_AMOUNT minus [SUM for all payment estimate projects (CURRENT_INSTALLED_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] minus [SUM for all payment estimate projects (CURRENT_INSTALLED_AMOUNT where associated ITEMSOURCE is "Change Order" or "Modified Change Order")] plus TOTAL_GROSS_ITEM_ADJUSTMENT_AMOUNT minus "Installed Amount for Subcontractors for All Payment Estimate Items for All Payment Estimate Projects" plus TOTAL_GROSS_ESTIMATE_CONTRACT_ ADJUSTMENT_PROJECT_DISTRIBUTION_AMOUNT = TOTAL_NET_AMOUNT_FOR_RETAINAGE_CALCULATION |
31 |
Work per period |
Retainage Calculation: Yes Retainage for Contract or Project: Project Payment Estimate's Contract has a Project Fund where FUNDTYPE is set to Federal Retainage Exempt for Subcontract Items: Yes Retainage Exempt for Stockpiles: Yes Contract Retainage Base: Award |
Note: If no Federal Project Fund exists for the Contract, the system uses the calculations in Row 27. For each Payment Estimate Item for Payment Estimate Project where associated ITEMSOURCE is equal to "Original" or "Modified Original" AND where an associated DWR_POSTING_QTY (for current payment estimate project) has CONTRACTOR not equal to PRIMEVENDOR_ID, calculate the percentage of work completed by the subcontractors for the Payment Estimate Item: "Percentage of work by Subcontractors for Payment Estimate Item" = Divide [SUM (DWR_POSTING_QTY associated to current PAYMENT ESTIMATE ITEM where CONTRACTOR does not equal PRIMEVENDOR_ID)] by CURRENT_INSTALLED_QUANTITY Next, calculate the installed amount for the subcontractors for the Payment Estimate Item: "Installed Amount for Subcontractors for Payment Estimate Item" = Multiply "Percentage of work by Subcontractors for Payment Estimate Item" by CURRENT_INSTALLED_AMOUNT Then, sum the "Installed Amount for Subcontractors for Payment Estimate Item" for all Payment Estimate Items: "Installed Amount for Subcontractors for All Payment Estimate Items" = SUM across all Payment Estimate Items ("Installed Amount for Subcontractors for Payment Estimate Item") CURRENT_ITEM_PAID_GROSS_AMOUNT minus [SUM for current payment estimate project (CURRENT_INSTALLED_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] minus [SUM for current payment estimate project (CURRENT_INSTALLED_AMOUNT where associated ITEMSOURCE is "Change Order" or "Modified Change Order")] plus [CURRENT_GROSS_ITEM_ADJUSTMENT_AMOUNT - SUM (ITEM_ADJUSTMENT_AMOUNT where ITEM_ADJUSTMENT_TYPE is "Construction Stockpile")] minus "Installed Amount for Subcontractors for All Payment Estimate Items" (as calculated above) plus CURRENT_GROSS_ESTIMATE_CONTRACT_ ADJUSTMENT_PROJECT_DISTRIBUTION_AMOUNT = CURRENT_NET_AMOUNT_FOR_RETAINAGE_CALCULATION |
32 |
Work in place |
Retainage Calculation: Yes Retainage for Contract or Project: Project Payment Estimate's Contract has a Project Fund where FUNDTYPE is set to Federal Retainage Exempt for Subcontract Items: Yes Retainage Exempt for Stockpiles: Yes Contract Retainage Base: Award |
Note: If no Federal Project Fund exists for the Contract, the system uses the calculations in Row 28. For every Payment Estimate Item that has been included on a Payment Estimate Project for the current Payment Estimate Project's Contract Project where associated ITEMSOURCE is equal to "Original" or "Modified Original" AND where an associated DWR_POSTING_QTY has CONTRACTOR not equal to PRIMEVENDOR_ID, calculate the percentage of work completed by the subcontractors for the Payment Estimate Item: "Percentage of work by Subcontractors for Payment Estimate Item across all Payment Estimate Projects" = Divide [SUM (DWR_POSTING_QTY associated to PAYMENT ESTIMATE ITEM where CONTRACTOR does not equal PRIMEVENDOR_ID)] by (CURRENT_INSTALLED_QUANTITY + REVIOUS_TOTAL_INSTALLED_QUANTITY) Next, calculate the installed amount for the subcontractors for the Payment Estimate Item: "Installed Amount for Subcontractors for Payment Estimate Item across all Payment Estimate Projects" = Multiply "Percentage of work by Subcontractors for Payment Estimate Item across all Payment Estimate Projects" by [(CURRENT_INSTALLED_QUANTITY + REVIOUS_TOTAL_INSTALLED_QUANTITY) multiplied by the unit price of the item]. Then, sum the "Installed Amount for Subcontractors for Payment Estimate Item across all Payment Estimate Projects" for all Payment Estimate Items: "Installed Amount for Subcontractors for All Payment Estimate Items for All Payment Estimate Projects" = SUM across all Payment Estimate Items ("Installed Amount for Subcontractors for Payment Estimate Item across all Payment Estimate Projects") TOTAL_ITEM_PAID_GROSS_AMOUNT minus [SUM for all payment estimate projects (CURRENT_INSTALLED_AMOUNT where associated EXEMPT_FROM_RETAINAGE_IND is "Yes")] minus [SUM for all payment estimate projects (CURRENT_INSTALLED_AMOUNT where associated ITEMSOURCE is "Change Order" or "Modified Change Order")] plus [TOTAL_GROSS_ITEM_ADJUSTMENT_AMOUNT - SUM for all payment estimate projects (ITEM_ADJUSTMENT_AMOUNT where ITEM_ADJUSTMENT_TYPE is "Construction Stockpile")] minus "Installed Amount for Subcontractors for All Payment Estimate Items for All Payment Estimate Projects" plus TOTAL_GROSS_ESTIMATE_CONTRACT_ ADJUSTMENT_PROJECT_DISTRIBUTION_AMOUNT= TOTAL_NET_AMOUNT_FOR_RETAINAGE_CALCULATION |
The calculations used by the system to determine when the amount required to trigger the system to calculate retainage has been reached depend on the retainage trigger base setting, the retainage method, and the settings for a number of other agency options. The following table provides detailed calculations for each potential configuration of these factors.
Row |
Retainage Method |
Agency Option Settings |
Calculations |
33 |
Work per period |
Retainage Calculation: Yes Retainage for Contract or Project: Contract Contract Retainage Trigger Base: Current |
'Trigger Amount' = RETAINAGE_TRIGGER_PERCENTAGE multiplied by CURRENTCONTRACTAMOUNT If TOTAL_NET_AMOUNT_FOR_RETAINAGE_CALCULATION is greater than or equal to 'Trigger Amount', then system will calculate retainage for the Contract. Otherwise, no further retainage logic is performed by the system. |
34 |
Work in place |
Retainage Calculation: Yes Retainage for Contract or Project: Contract Contract Retainage Trigger Base: Current |
If TOTAL _NET_AMOUNT_FOR_RETAINAGE_CALCULATION is greater than or equal to 'Trigger Amount,' then system will calculate retainage for the Contract. Otherwise, no further retainage logic is performed by the system. |
35 |
Work per period |
Retainage Calculation: Yes Retainage for Contract or Project: Contract Contract Retainage Trigger Base: Award |
If TOTAL_NET_AMOUNT_FOR_RETAINAGE_CALCULATION is greater than or equal to 'Trigger Amount', then system will calculate retainage for the Contract. Otherwise, no further retainage logic is performed by the system. |
36 |
Work in place |
Retainage Calculation: Yes Retainage for Contract or Project: Contract Contract Retainage Trigger Base: Award |
If TOTAL _NET_AMOUNT_FOR_RETAINAGE_CALCULATION is greater than or equal to 'Trigger Amount,' then system will calculate retainage for the Contract. Otherwise, no further retainage logic is performed by the system. |
37 |
Work per period |
Retainage Calculation: Yes Retainage for Contract or Project: Project Contract Retainage Trigger Base: Current |
'Trigger Amount' = RETAINAGE_TRIGGER_PERCENTAGE multiplied by CURRENTPROJECTAMOUNT If TOTAL_NET_AMOUNT_FOR_RETAINAGE_CALCULATION is greater than or equal to 'Trigger Amount', then system will calculate retainage for the Contract Project. Otherwise, no further retainage logic is performed by the system. |
38 |
Work in place |
Retainage Calculation: Yes Retainage for Contract or Project: Project Contract Retainage Trigger Base: Current |
'Trigger Amount' = RETAINAGE_TRIGGER_PERCENTAGE multiplied by CURRENTPROJECTAMOUNT If TOTAL _NET_AMOUNT_FOR_RETAINAGE_CALCULATION is greater than or equal to 'Trigger Amount', then system will calculate retainage for the Contract Project. Otherwise, no further retainage logic is performed by the system. |
39 |
Work per period |
Retainage Calculation: Yes Retainage for Contract or Project: Project Contract Retainage Trigger Base: Award |
'Trigger Amount' = RETAINAGE_TRIGGER_PERCENTAGE multiplied by ORIGINALPROJECTAMOUNT If TOTAL_NET_AMOUNT_FOR_RETAINAGE_CALCULATION is greater than or equal to 'Trigger Amount', then system will calculate retainage for the Contract Project. Otherwise, no further retainage logic is performed by the system. |
40 |
Work in place |
Retainage Calculation: Yes Retainage for Contract or Project: Project Contract Retainage Trigger Base: Award |
If TOTAL _NET_AMOUNT_FOR_RETAINAGE_CALCULATION is greater than or equal to 'Trigger Amount', then system will calculate retainage for the Contract Project. Otherwise, no further retainage logic is performed by the system. |
Row |
Retainage Method |
Agency Option Settings |
Calculations |
41 |
Work per period |
Retainage Calculation: Yes Retainage for Contract or Project: Contract |
CURRENT_GROSS_RETAINAGE_AMOUNT = (RETAINAGE_PERCENTAGE multiplied by CURRENT_NET_AMOUNT_FOR_RETAINAGE_CALCULATION) + RETAINAGE_LUMP_SUM_AMT |
42 |
Work in place |
Retainage Calculation: Yes Retainage for Contract or Project: Contract |
CURRENT_GROSS_RETAINAGE_AMOUNT = absolute value (TOTAL_GROSS RETAINAGE_AMOUNT from previous payment estimate) - [(RETAINAGE_PERCENTAGE multiplied by TOTAL_NET_AMOUNT_FOR_RETAINAGE_CALCULATION) + RETAINAGE_LUMP_SUM_AMT] |
43 |
Work per period |
Retainage Calculation: Yes Retainage for Contract or Project: Project |
CURRENT_GROSS_RETAINAGE_AMOUNT = (RETAINAGE_PERCENTAGE multiplied by CURRENT_NET_AMOUNT_FOR_RETAINAGE_CALCULATION) + RETAINAGE_LUMP_SUM_AMT
|
44 |
Work in place |
Retainage Calculation: Yes Retainage for Contract or Project: Project |
CURRENT_GROSS_RETAINAGE_AMOUNT = absolute value (TOTAL_GROSS RETAINAGE_AMOUNT from previous payment estimate project) - [(RETAINAGE_PERCENTAGE multiplied by TOTAL_NET_AMOUNT_FOR_RETAINAGE_CALCULATION) + RETAINAGE_LUMP_SUM_AMT] |
Row |
Agency Option Settings |
Calculations |
45 |
Retainage Calculation: Yes Retainage for Contract or Project: Contract |
The system calculates a 'Maximum Allowed Dollar Amount' for the Contract as follows: - If RETAINAGE_MAX_DOLLAR_AMT is populated, 'Maximum Allowed Dollar Amount' = RETAINAGE_MAX_DOLLAR_AMT. - If RETAINAGE_MAX_PERCENTAGE is populated and the RETAINAGE_BASE is "Current Amount", 'Maximum Allowed Dollar Amount' = RETAINAGE_MAX_PERCENTAGE multiplied by CURRENTCONTRACTAMOUNT. - If RETAINAGE_MAX_PERCENTAGE is populated and the RETAINAGE_BASE is "Award Amount", 'Maximum Allowed Dollar Amount' = RETAINAGE_MAX_PERCENTAGE multiplied by AWARDEDAMOUNT. Then, the system compares what will be the resultant and absolute value for TOTAL_GROSS_RETAINAGE_AMOUNT (PREVIOUS_GROSS_RETAINAGE_AMOUNT + CURRENT_GROSS_RETAINAGE_AMOUNT) to the 'Maximum Allowed Dollar Amount'. - If TOTAL_GROSS_RETAINAGE_AMOUNT is less than or equal to 'Maximum Allowed Dollar Amount', the system sets CURRENT_GROSS_RETAINAGE_AMOUNT to the calculated value (from row 41 or 42). - If absolute value (TOTAL_GROSS_RETAINAGE_AMOUNT) > 'Maximum Allowed Dollar Amount', the system updates CURRENT_GROSS_RETAINAGE_AMOUNT so that absolute value (TOTAL_GROSS_RETAINAGE_AMOUNT) = 'Maximum Allowed Dollar Amount'. Then, TOTAL_GROSS_RETAINAGE_AMOUNT = PREVIOUS_GROSS_RETAINAGE_AMOUNT + CURRENT_GROSS_RETAINAGE_AMOUNT. |
46 |
Retainage Calculation: Yes Retainage for Contract or Project: Project |
The system calculates a 'Maximum Allowed Dollar Amount' for the Contract Project as follows: - If RETAINAGE_MAX_DOLLAR_AMT is populated, 'Maximum Allowed Dollar Amount' = RETAINAGE_MAX_DOLLAR_AMT. - If RETAINAGE_MAX_PERCENTAGE is populated and the RETAINAGE_BASE is "Current Amount", 'Maximum Allowed Dollar Amount' = RETAINAGE_MAX_PERCENTAGE multiplied by CURRENTPROJECTAMOUNT. - If RETAINAGE_MAX_PERCENTAGE is populated and the RETAINAGE_BASE is "Award Amount", 'Maximum Allowed Dollar Amount' = RETAINAGE_MAX_PERCENTAGE multiplied by ORIGINALPROJECTAMOUNT. Then, the system compares what will be the resultant and absolute value for TOTAL_GROSS_RETAINAGE_AMOUNT (PREVIOUS_GROSS_RETAINAGE_AMOUNT + CURRENT_GROSS_RETAINAGE_AMOUNT) to the 'Maximum Allowed Dollar Amount'. If TOTAL_GROSS_RETAINAGE_AMOUNT is less than or equal to 'Maximum Allowed Dollar Amount', the system sets CURRENT_GROSS_RETAINAGE_AMOUNT to the calculated value (from row 43 or 44). If absolute value (TOTAL_GROSS_RETAINAGE_AMOUNT) > 'Maximum Allowed Dollar Amount', the system updates CURRENT_GROSS_RETAINAGE_AMOUNT so that absolute value (TOTAL_GROSS_RETAINAGE_AMOUNT) = 'Maximum Allowed Dollar Amount'. Then, TOTAL_GROSS_RETAINAGE_AMOUNT = PREVIOUS_GROSS_RETAINAGE_AMOUNT + CURRENT_GROSS_RETAINAGE_AMOUNT. |
Note: If no Contract Security Accounts exist for Payment Estimate's Contract or if all associated Reference Vendor Security Accounts have an Amount Available = 0.00, this calculation is skipped and the system executes the calculations in row 49.
Row |
Agency Option Settings |
Calculations |
47 |
Retainage Calculation: Yes Retainage for Contract or Project: Contract |
The system calculates "Previous Withheld Cash + Current Retainage Required" for Payment Estimate. This is the amount of previously withheld cash and the amount of retainage required now based on the current Payment Estimate. It is calculated as follows: absolute value SUM (PREVIOUS_CASH_RETAINAGE_AMOUNT + CURRENT_GROSS_RETAINAGE_AMOUNT). The system calculates "Total Amount Available from Contract's Security Accounts". This is the total amount available in Reference Vendor Security Accounts for the Prime Contractor of the Payment Estimate's Contract. It is calculated as follows: SUM (AMT_AVAILABLE) for all accounts associated to the Prime Contractor of the Payment Estimate's Contract (PRIMEVENDOR_ID). The system compares "Previous Withheld Cash + Current Retainage Required" to "Total Amount Available from Contract's Security Accounts." If "Total Amount Available from Contract's Security Accounts" is greater than or equal to "Withheld Cash + Current Retainage Required," then: If PAYMENT ESTIMATE.PREVIOUS_CASH_RETAINAGE_AMOUNT does not equal 0.00, system creates a PAYMENT ESTIMATE CONTRACT ADJUSTMENT where: COMMENTS = initial value, NULL CONTRACT_ADJUSTMENT_AMOUNT = absolute value PREVIOUS_CASH_RETAINAGE_AMOUNT CONTRACT_ADJUSTMENT_DATE = CREATION_DT (for associated PAYMENT ESTIMATE) CONTRACT_ADJUSTMENT_ID = initial value, system generated ID CONTRACT_ADJUSTMENT_TYPE = RETAINAGE CREATOR_ID = ProcessName CURRENT_NUMBER_TIME_UNITS = initial value, NULL TIME_ID = initial value, NULL System creates a PAYMENT ESTIMATE CONTRACT ADJUSTMENT PROJECT DISTRIBUTION record(s) for the Payment Estimate Contract Adjustment above where: If agency option CONTRACT ADJUSTMENT DISTRIBUTION is set to "Bid", system creates the record as follows for each Contract Project associated to the Payment Estimate's Contract: - DISTRIBUTION_AMOUNT = CONTRACT_ADJUSTMENT_AMOUNT x (ORIGINALPROJECTAMOUNT/AWARDEDAMOUNT) - DISTRIBUTION_PERCENTAGE = (ORIGINALPROJECTAMOUNT/AWARDEDAMOUNT) x 100.00 If agency option CONTRACT ADJUSTMENT DISTRIBUTION is set to "Current", system creates the record as follows for each Contract Project associated to the Payment Estimate's Contract: - DISTRIBUTION_AMOUNT = CONTRACT_ADJUSTMENT_AMOUNT x (CURRENTPROJECTAMOUNT/CURRENTCONTRACTAMOUNT) - DISTRIBUTION_PERCENTAGE = (CURRENTPROJECTAMOUNT/CURRENTCONTRACTAMOUNT) x 100.00 Next, system gets REFERENCE VENDOR SECURITY ACCOUNT (associated to CONTRACT SECURITY ACCOUNT) where TYPE = 'Securities', AMT_AVAILABLE does not equal 0.00 and has earliest CREATEDDATE of all accounts with TYPE = 'Securities'. If AMT_AVAILABLE is greater than or equal to "Withheld Cash + Current Retainage Required", system creates PAYMENT ESTIMATE SECURITIES ENCUMBRANCE record for the account where: - ACCOUNT_ID = ACCOUNT_ID - CONTRACT_ID = CONTRACT_ID for associated Payment Estimate - ESTIMATE_NBR = PAYMENT ESTIMATE.ESTIMATE_NUMBER - REFVENDOR_ID = CONTRACT SECURITY ACCOUNT.REFVENDOR_ID - SECURITIES_ADJUSTMENT_AMT = "Withheld Cash + Current Retainage Required" stored as negative value If AMT_AVAILABLE < "Withheld Cash + Current Retainage Required", system creates PAYMENT ESTIMATE SECURITIES ENCUMBRANCE record for the account where: - ACCOUNT_ID = CONTRACT SECURITY ACCOUNT.ACCOUNT_ID - CONTRACT_ID = CONTRACT_ID for associated Payment Estimate - ESTIMATE_NBR = PAYMENT ESTIMATE.ESTIMATE_NUMBER - REFVENDOR_ID = CONTRACT SECURITY ACCOUNT.REFVENDOR_ID - SECURITIES_ADJUSTMENT_AMT = REFERENCE VENDOR SECURITY ACCOUNT.AMT_AVAILABLE stored as negative value The above logic of evaluating a REFERENCE VENDOR SECURITY ACCOUNT (associated to CONTRACT SECURITY ACCOUNT) is repeated by system evaluating Security Account with next earliest CREATEDDATE, TYPE = 'Securities' and AMT_AVAILABLE does not equal 0.00. This continues until full "Withheld Cash + Current Retainage Required" amount is encumbered by Contract Security Account(s) [i.e., "Withheld Cash + Current Retainage Required" = absolute value SUM (SECURITIES_ADJUSTMENT_AMT) for current Payment Estimate] or until AMT_AVAILABLE = 0.00 for associated REFERENCE VENDOR SECURITY ACCOUNT(s) where TYPE = 'Securities.' If full "Withheld Cash + Current Retainage Required" amount is NOT encumbered by all associated REFERENCE VENDOR SECURITY ACCOUNT(s) where TYPE = 'Securities,' the above logic is repeated for each associated REFERENCE VENDOR SECURITY ACCOUNT where TYPE = 'Escrow', AMT_AVAILABLE ≠ 0.00 and in order by CREATEDDATE until full "Withheld Cash + Current Retainage Required" amount is encumbered. If "Total Amount Available from Contract's Security Accounts" is less than "Withheld Cash + Current Retainage Required", then System creates a PAYMENT ESTIMATE CONTRACT ADJUSTMENT where: COMMENTS = initial value, NULL CONTRACT_ADJUSTMENT_AMOUNT = absolute value PREVIOUS_CASH_RETAINAGE_AMOUNT - ("Previous Withheld Cash + Current Retainage Required" - "Total Amount Available from Contract's Security Accounts") CONTRACT_ADJUSTMENT_DATE = CREATION_DT (for associated PAYMENT ESTIMATE) CONTRACT_ADJUSTMENT_ID = initial value, system generated ID CONTRACT_ADJUSTMENT_TYPE = RETAINAGE CREATOR_ID = ProcessName CURRENT_NUMBER_TIME_UNITS = initial value, NULL TIME_ID = initial value, NULL Next, for each associated REFERENCE VENDOR SECURITY ACCOUNT where AMT _AVAILABLE does not equal 0.00, system creates a PAYMENT ESTIMATE SECURITIES ENCUMBRANCE record for the account where: ACCOUNT_ID = CONTRACT SECURITY ACCOUNT.ACCOUNT_ID CONTRACT_ID = CONTRACT_ID for associated Payment Estimate ESTIMATE_NBR = PAYMENT ESTIMATE.ESTIMATE_NUMBER REFVENDOR_ID = CONTRACT SECURITY ACCOUNT.REFVENDOR_ID SECURITIES_ADJUSTMENT_AMT = AMT_AVAILABLE stored as negative value For each REFERENCE VENDOR SECURITY ACCOUNT where the system created a new PAYMENT ESTIMATE SECURITIES ENCUMBRANCE record for the current Payment Estimate, the system updates the following attributes: For REFERENCE VENDOR SECURITY ACCOUNT: AMT_AVAILABLE incremented by SECURITIES_ADJUSTMENT_AMT For CONTRACT SECURITY ACCOUNT (associated to REFERENCE VENDOR SECURITY ACCOUNT): SECURITIES_ENCUMBRANCE_AMT incremented by absolute value (SECURITIES_ADJUSTMENT_AMT) DIFFERENCE_AMT = REQUIRED_AMT - SECURITIES_ENCUMBRANCE_AMT For all REFERENCE VENDOR SECURITY ACCOUNT(s) associated to the Payment Estimate's Contract's Prime Contractor (PRIMEVENDOR_ID) and having a CONTRACT SECURITY ACCOUNT for the Payment Estimate's Contract, the system updates the following attributes: For REFERENCE VENDOR SECURITY ACCOUNT: TOTAL_RETAINAGE_REQUIRED incremented by absolute value (CURRENT_GROSS_RETAINAGE_AMOUNT) For CONTRACT SECURITY ACCOUNT: REQUIRED_AMT = absolute value (CURRENT_GROSS_RETAINAGE_AMOUNT + PREVIOUS_GROSS_RETAINAGE_AMOUNT) Last, system updates the following attributes for class PAYMENT ESTIMATE: CURRENT_SECURITIES_RETAINAGE_AMOUNT = SUM (ADJUSTMENT_AMT for CONTRACT_ID and ESTIMATE_NBR of associated Payment Estimate where associated REFERENCE VENDOR SECURITY ACCOUNT.TYPE = "Security".) TOTAL_SECURITIES_RETAINAGE_AMOUNT = PREVIOUS_SECURITIES_RETAINAGE_AMOUNT + CURRENT_SECURITIES_RETAINAGE_AMOUNT CURRENT_ESCROW_RETAINAGE_AMOUNT = SUM (ADJUSTMENT_AMT for CONTRACT_ID and ESTIMATE_NBR of associated Payment Estimate where associated REFERENCE VENDOR SECURITY ACCOUNT.TYPE = "Escrow".) TOTAL_ESCROW_RETAINAGE_AMOUNT = PREVIOUS_ESCROW_RETAINAGE_AMOUNT + CURRENT_ESCROW_RETAINAGE_AMOUNT CURRENT_NONCASH_RETAINAGE_AMOUNT = CURRENT_SECURITIES_RETAINAGE_AMOUNT + CURRENT_ESCROW_RETAINAGE_AMOUNT TOTAL_NONCASH_RETAINAGE_AMOUNT = TOTAL_SECURITIES_RETAINAGE_AMOUNT + TOTAL_ESCROW_RETAINAGE_AMOUNT |
48 |
Retainage Calculation: Yes Retainage for Contract or Project: Project |
The system calculates "Previous Withheld Cash + Current Retainage Required" for Payment Estimate Project. This is the amount of previously withheld cash and the amount of retainage required now based on the current Payment Estimate Project. It is calculated as follows: absolute value SUM (PREVIOUS_CASH_RETAINAGE_AMOUNT + CURRENT_GROSS_RETAINAGE_AMOUNT). The system calculates "Total Amount Available from Contract's Security Accounts." This is the total amount available in Reference Vendor Security Accounts for the Prime Contractor of the associated Payment Estimate's Contract. It is calculated as follows: SUM (AMT_AVAILABLE) for all accounts associated to the Prime Contractor of the Payment Estimate's Contract (PRIMEVENDOR_ID). The system compares "Previous Withheld Cash + Current Retainage Required" to "Total Amount Available from Contract's Security Accounts." If "Total Amount Available from Contract's Security Accounts" is greater than or equal to "Withheld Cash + Current Retainage Required", then: If PREVIOUS_CASH_RETAINAGE_AMOUNT does not equal 0.00, system creates a PAYMENT ESTIMATE CONTRACT ADJUSTMENT where: COMMENTS = initial value, NULL CONTRACT_ADJUSTMENT_AMOUNT = absolute value PREVIOUS_CASH_RETAINAGE_AMOUNT CONTRACT_ADJUSTMENT_DATE = PAYMENT ESTIMATE PROJECT.CREATION_DT CONTRACT_ADJUSTMENT_ID = initial value, system generated ID CONTRACT_ADJUSTMENT_TYPE = RETAINAGE CREATOR_ID = ProcessName CURRENT_NUMBER_TIME_UNITS = initial value, NULL TIME_ID = initial value, NULL System creates a read-only PAYMENT ESTIMATE CONTRACT ADJUSTMENT PROJECT DISTRIBUTION record for the Estimate Contract Adjustment above where: DISTRIBUTION_AMOUNT = CONTRACT_ADJUSTMENT_AMOUNT DISTRIBUTION_PERCENTAGE = 100.00 Next, system gets REFERENCE VENDOR SECURITY ACCOUNT (associated to CONTRACT SECURITY ACCOUNT) where TYPE = 'Securities', AMT_AVAILABLE does not equal 0.00 and has earliest CREATEDDATE of all accounts with TYPE = 'Securities'. If REFERENCE VENDOR SECURITY ACCOUNT.AMT_AVAILABLE is greater than or equal to "Withheld Cash + Current Retainage Required", system creates PAYMENT ESTIMATE SECURITIES ENCUMBRANCE record for the account where: ACCOUNT_ID = CONTRACT SECURITY ACCOUNT.ACCOUNT_ID CONTRACT_ID = CONTRACT_ID for associated Payment Estimate ESTIMATE_NBR = PAYMENT ESTIMATE.ESTIMATE_NUMBER (for associated Payment Estimate) REFVENDOR_ID = CONTRACT SECURITY ACCOUNT.REFVENDOR_ID SECURITIES_ADJUSTMENT_AMT = "Withheld Cash + Current Retainage Required" stored as negative value If REFERENCE VENDOR SECURITY ACCOUNT.AMT_AVAILABLE < "Withheld Cash + Current Retainage Required", system creates PAYMENT ESTIMATE SECURITIES ENCUMBRANCE record for the account where: ACCOUNT_ID = CONTRACT SECURITY ACCOUNT.ACCOUNT_ID CONTRACT_ID = CONTRACT_ID for associated Payment Estimate ESTIMATE_NBR = PAYMENT ESTIMATE.ESTIMATE_NUMBER (for associated Payment Estimate) REFVENDOR_ID = CONTRACT SECURITY ACCOUNT.REFVENDOR_ID SECURITIES_ADJUSTMENT_AMT = REFERENCE VENDOR SECURITY ACCOUNT.AMT_AVAILABLE stored as negative value The above logic of evaluating a REFERENCE VENDOR SECURITY ACCOUNT (associated to CONTRACT SECURITY ACCOUNT) is repeated by system evaluating Security Account with next earliest CREATEDDATE, TYPE = 'Securities' and AMT_AVAILABLE does not equal 0.00. This continues until full "Withheld Cash + Current Retainage Required" amount is encumbered by Contract Security Account(s) [i.e., "Withheld Cash + Current Retainage Required" = absolute value SUM (SECURITIES_ADJUSTMENT_AMT) for Payment Estimate associated to current Payment Estimate Project] or until AMT_AVAILABLE = 0.00 for associated REFERENCE VENDOR SECURITY ACCOUNT(s) where TYPE = 'Securities'. If full "Withheld Cash + Current Retainage Required" amount is NOT encumbered by all associated REFERENCE VENDOR SECURITY ACCOUNT(s) where TYPE = 'Securities', the above logic is repeated for each associated REFERENCE VENDOR SECURITY ACCOUNT where TYPE = 'Escrow', AMT_AVAILABLE does not equal 0.00 and in order by CREATEDDATE until full "Withheld Cash + Current Retainage Required" amount is encumbered. If "Total Amount Available from Contract's Security Accounts"< "Withheld Cash + Current Retainage Required", then System creates a PAYMENT ESTIMATE CONTRACT ADJUSTMENT where: COMMENTS = initial value, NULL CONTRACT_ADJUSTMENT_AMOUNT = absolute value PREVIOUS_CASH_RETAINAGE_AMOUNT - ("Previous Withheld Cash + Current Retainage Required" - "Total Amount Available from Contract's Security Accounts") CONTRACT_ADJUSTMENT_DATE = PAYMENT ESTIMATE PROJECT.CREATION_DT CONTRACT_ADJUSTMENT_ID = initial value, system generated ID CONTRACT_ADJUSTMENT_TYPE = RETAINAGE CREATOR_ID = ProcessName CURRENT_NUMBER_TIME_UNITS = initial value, NULL TIME_ID = initial value, NULL Next, for each associated REFERENCE VENDOR SECURITY ACCOUNT where AMT _AVAILABLE does not equal 0.00, system creates a PAYMENT ESTIMATE SECURITIES ENCUMBRANCE record for the account where: ACCOUNT_ID = CONTRACT SECURITY ACCOUNT.ACCOUNT_ID CONTRACT_ID = CONTRACT_ID for associated Payment Estimate ESTIMATE_NBR = PAYMENT ESTIMATE.ESTIMATE_NUMBER (for associated Payment Estimate) REFVENDOR_ID = CONTRACT SECURITY ACCOUNT.REFVENDOR_ID SECURITIES_ADJUSTMENT_AMT = REFERENCE VENDOR SECURITY ACCOUNT.AMT_AVAILABLE stored as negative value For each REFERENCE VENDOR SECURITY ACCOUNT where the system created a new PAYMENT ESTIMATE SECURITIES ENCUMBRANCE record for the current associated Payment Estimate, the system updates the following attributes: For REFERENCE VENDOR SECURITY ACCOUNT: AMT_AVAILABLE incremented by PAYMENT ESTIMATE SECURITIES ENCUMBRANCE.SECURITIES_ADJUSTMENT_AMT For CONTRACT SECURITY ACCOUNT (associated to REFERENCE VENDOR SECURITY ACCOUNT): SECURITIES_ENCUMBRANCE_AMT incremented by absolute value (PAYMENT ESTIMATE SECURITIES ENCUMBRANCE.SECURITIES_ADJUSTMENT_AMT) DIFFERENCE_AMT = REQUIRED_AMT - SECURITIES_ENCUMBRANCE_AMT For all REFERENCE VENDOR SECURITY ACCOUNT(s) associated to the Payment Estimate's Contract's Prime Contractor (PRIMEVENDOR_ID) and having a CONTRACT SECURITY ACCOUNT for the Payment Estimate's Contract, the system updates the following attributes: For REFERENCE VENDOR SECURITY ACCOUNT: TOTAL_RETAINAGE_REQUIRED incremented by absolute value (PAYMENT ESTIMATE PROJECT.CURRENT_GROSS_RETAINAGE_AMOUNT) For CONTRACT SECURITY ACCOUNT: REQUIRED_AMT = absolute value (PAYMENT ESTIMATE PROJECT.CURRENT_GROSS_RETAINAGE_AMOUNT + PAYMENT ESTIMATE PROJECT.PREVIOUS_GROSS_RETAINAGE_AMOUNT) Last, system updates the following attributes for class PAYMENT ESTIMATE PROJECT: CURRENT_SECURITIES_RETAINAGE_AMOUNT = SUM (PAYMENT ESTIMATE SECURITIES ENCUMBRANCE.ADJUSTMENT_AMT for CONTRACT_ID and ESTIMATE_NBR of associated Payment Estimate where associated REFERENCE VENDOR SECURITY ACCOUNT.TYPE = "Security".) TOTAL_SECURITIES_RETAINAGE_AMOUNT = PREVIOUS_SECURITIES_RETAINAGE_AMOUNT + CURRENT_SECURITIES_RETAINAGE_AMOUNT CURRENT_ESCROW_RETAINAGE_AMOUNT = SUM (PAYMENT ESTIMATE SECURITIES ENCUMBRANCE.ADJUSTMENT_AMT for CONTRACT_ID and ESTIMATE_NBR of associated Payment Estimate where associated REFERENCE VENDOR SECURITY ACCOUNT.TYPE = "Escrow".) TOTAL_ESCROW_RETAINAGE_AMOUNT = PREVIOUS_ESCROW_RETAINAGE_AMOUNT + CURRENT_ESCROW_RETAINAGE_AMOUNT CURRENT_NONCASH_RETAINAGE_AMOUNT = CURRENT_SECURITIES_RETAINAGE_AMOUNT + CURRENT_ESCROW_RETAINAGE_AMOUNT TOTAL_NONCASH_RETAINAGE_AMOUNT = TOTAL_SECURITIES_RETAINAGE_AMOUNT + TOTAL_ESCROW_RETAINAGE_AMOUNT. |
Note: No Contract Security Accounts exist for Payment Estimate's Contract or all associated Reference Vendor Security Accounts have an Amount Available = 0.00.
Row |
Agency Option Settings |
Calculations |
49 |
Retainage Calculation: Yes Retainage for Contract or Project: Contract Contract Adjustment Distribution: Bid
|
CURRENT_CASH_RETAINAGE_AMOUNT = CURRENT_GROSS_RETAINAGE_AMOUNT System creates a PAYMENT ESTIMATE CONTRACT ADJUSTMENT record where: - COMMENTS = initial value, NULL - CONTRACT_ADJUSTMENT_AMOUNT = CURRENT_CASH_RETAINAGE_AMOUNT - CONTRACT_ADJUSTMENT_DATE = CREATION_DT - CONTRACT_ADJUSTMENT_ID = initial value, system generated ID - CONTRACT_ADJUSTMENT_TYPE = RETAINAGE - CREATOR_ID = ProcessName - CURRENT_NUMBER_TIME_UNITS = initial value, NULL - TIME_ID = initial value, NULL Next, the system creates PAYMENT ESTIMATE CONTRACT ADJUSTMENT PROJECT DISTRIBUTION record(s) as follows for each Contract Project associated with the Payment Estimate's Contract: - DISTRIBUTION_AMOUNT = CONTRACT_ADJUSTMENT_AMOUNT x (ORIGINALPROJECTAMOUNT/AWARDEDAMOUNT) - DISTRIBUTION_PERCENTAGE = (ORIGINALPROJECTAMOUNT/AWARDEDAMOUNT) x 100.00 |
50 |
Retainage Calculation: Yes Retainage for Contract or Project: Contract Contract Adjustment Distribution: Current |
CURRENT_CASH_RETAINAGE_AMOUNT = CURRENT_GROSS_RETAINAGE_AMOUNT System creates a PAYMENT ESTIMATE CONTRACT ADJUSTMENT record where: - COMMENTS = initial value, NULL - CONTRACT_ADJUSTMENT_AMOUNT = CURRENT_CASH_RETAINAGE_AMOUNT - CONTRACT_ADJUSTMENT_DATE = CREATION_DT - CONTRACT_ADJUSTMENT_ID = initial value, system generated ID - CONTRACT_ADJUSTMENT_TYPE = RETAINAGE - CREATOR_ID = ProcessName - CURRENT_NUMBER_TIME_UNITS = initial value, NULL - TIME_ID = initial value, NULL Next, the system creates PAYMENT ESTIMATE CONTRACT ADJUSTMENT PROJECT DISTRIBUTION record(s) as follows for each Contract Project associated to the Payment Estimate's Contract: - DISTRIBUTION_AMOUNT = CONTRACT_ADJUSTMENT_AMOUNT x (CURRENTPROJECTAMOUNT / CURRENTCONTRACTAMOUNT) - DISTRIBUTION_PERCENTAGE = (CURRENTPROJECTAMOUNT/CURRENTCONTRACTAMOUNT) x 100.00 |
51 |
Retainage Calculation: Yes Retainage for Contract or Project: Project |
CURRENT_CASH_RETAINAGE_AMOUNT = CURRENT_GROSS_RETAINAGE_AMOUNT System creates a PAYMENT ESTIMATE CONTRACT ADJUSTMENT record where: - COMMENTS = initial value, NULL - CONTRACT_ADJUSTMENT_AMOUNT = CURRENT_CASH_RETAINAGE_AMOUNT - CONTRACT_ADJUSTMENT_DATE = CREATION_DT (for associated PAYMENT ESTIMATE) - CONTRACT_ADJUSTMENT_ID = initial value, system generated ID - CONTRACT_ADJUSTMENT_TYPE = RETAINAGE - CREATOR_ID = ProcessName - CURRENT_NUMBER_TIME_UNITS = initial value, NULL - TIME_ID = initial value, NULL System creates a read-only PAYMENT ESTIMATE CONTRACT ADJUSTMENT PROJECT DISTRIBUTION record where: - DISTRIBUTION_AMOUNT = CONTRACT_ADJUSTMENT_AMOUNT - DISTRIBUTION_PERCENTAGE = 100.00 |
Row |
Agency Option Settings |
Calculations |
52 |
Retainage Calculation: Yes Retainage for Contract or Project: Contract |
TOTAL_RETAINAGE_REQUIRED = SUM (TOTAL_GROSS_RETAINAGE_AMOUNT) for all Contracts that have Contract Security Accounts associated to the Reference Vendor Security Account. |
53 |
Retainage Calculation: Yes Retainage for Contract or Project: Project |
TOTAL_RETAINAGE_REQUIRED = SUM (TOTAL_GROSS_RETAINAGE_AMOUNT) for all Contract Projects associated to all the Contracts that have Contract Security Accounts associated to the Reference Vendor Security Account. |
Row |
Agency Option Settings |
Calculations |
54 |
Retainage Calculation: Yes Retainage for Contract or Project: Contract |
REQUIRED_AMT = TOTAL_GROSS_RETAINAGE_AMOUNT of last created Payment Estimate |
55 |
Retainage Calculation: Yes Retainage for Contract or Project: Project |
REQUIRED_AMT = SUM for all projects associated with contract (TOTAL_GROSS_RETAINAGE_AMOUNT from last created Payment Estimate) |
Row |
Agency Option Settings |
Calculations |
56 |
Retainage Calculation: Yes Retainage for Contract or Project: Contract |
DIFFERENCE_AMT = TOTAL_GROSS_RETAINAGE_AMOUNT (from last created Payment Estimate) - SECURITIES_ENCUMBRANCE_AMT |
57 |
Retainage Calculation: Yes Retainage for Contract or Project: Project |
DIFFERENCE_AMT = SUM for all projects associated to contract (TOTAL_GROSS_RETAINAGE_AMOUNT from last created Payment Estimate) - SECURITIES_ENCUMBRANCE_AMT |